Interfleet graduates win IMechE Railway Challenge

0

The first locomotive to be built at Derby Locomotive Works for 35 years, albeit one of 10 ¼” gauge, yesterday won the Institution of Mechanical Engineers (IMechE) first Railway Challenge competition.

The locomotive was manufactured at the Roundhouse in Derby by a team of Interfleet graduate engineers.

Competitors from Manchester Metropolitan University, Birmingham University and an independent team from Derby all took part in the event.

The Stapleford Miniature Railway, near Melton Mowbray, provided a test track for the teams to demonstrate how their locomotives met the competition’s performance criteria which concerned traction power, ride quality and, most importantly, the storage of energy during retardation to power the locomotive when required.

Stephen Head, Interfleet’s team leader, said that the most difficult part was energy storage, but added that seeing his team’s locomotive move for the first time was the best part of the competition.

Announcing the results, Bridget Eickhoff, IMechE Railway Division Chairman, said she was extremely impressed by the efforts of all of the teams, who had produced very different and innovative designs from the same specification.

As far as she was aware, the competition had seen the first hydrogen propelled locomotive with Birmingham University’s entry and she wondered how long it would be before innovations in this and future such competitions would appear in the real railway.

For the rules and technical specification for the IMechE’s Railway Challenge click here.

The Stapleford Miniature Railway holds its next open weekend on 26 / 27th August
.

Olympic train timetables published

1

Greater Anglia has published its timetable booklets for the Olympic Games.

The timetables are available in four regional variations covering the Mainline, West Anglia/Stansted Express, Southend & Metro and Rural routes operated by Greater Anglia.

Train times for the Games have already been published online on the Greater Anglia website.

The timetables include details of extra late-evening and additional weekend services that will be operating.

On Sundays more trains will operate, with a revised Saturday timetable running on key routes serving the Games.

During the period of the Olympic and Paralympic Games, Greater Anglia will be providing around an extra 150,000 seats each day on trains across its network serving London Liverpool Street, Stratford, other East London stations and the East Anglia region.

Ruud Haket, managing director of Greater Anglia, said: “The Greater Anglia team will be working together with Network Rail and our Games partners in making every effort to provide our regular customers and many visitors to the Games with the best possible service this summer.”

Bombardier to supply 39 additional Berlin trams

0

The Berlin Transport Authority (BVG) has ordered another 39 Flexity trams from Bombardier Transportation as part of an order worth around 134 million euros.

The new low-floor trams are part of an original agreement for 206 vehicles, which was signed in 2006.

The total number of Flexity Berlin trams ordered now stands at 142.

Klaus-Dietrich Matschke, executive director for trams at BVG, said: “With this order of 138 vehicles, BVG is responding to a positive increase in passenger numbers and growing its capacity for the future.”

The Flexity Berlin fleet now includes 38 long uni-directional vehicles, 53 short and 47 long bi-directional vehicles.

Delivery of the additional trams is expected to start in 2016.

The order ensures that the old Tatra trams will be made redundant by 2017.

Germar Wacker, president of light rail vehicles at Bombardier Transportation, said: “The call-off of another 39 vehicles by the BVG is yet another milestone in our long and successful cooperation.

“We are delighted that the vehicles are well received by the Berlin public.”

The newest tram from Bombardier, the Flexity 2, is planned for display during InnoTrans 2012 this September in Berlin.

Transport chief calls for tram-train investment

2

Public transport chief Geoff Inskip has urged the government to invest millions of pounds into tram-trains.

Mr Inskip called on the Department for Transport to set aside £100 million a year from the savings identified in the McNulty Report into improving efficiency in Britain’s rail industry to develop tram-train networks across the country.

Tram-train is a light-rail public transport system where trams are able to run on an urban network and on mainline railways shared with conventional trains.

He said: “Tram-train is a brilliant concept ripe for development – it combines the tram’s flexibility and accessibility with a train’s greater speed, and bridges the distance between main railway stations and a city centre.

“It is why I say the Government should set aside £100 million per annum from those savings they will be making from McNulty and ring fence that money for tram-train.

“In this way we can get on with delivering the Department for Transport’s agenda of delivering a better value for money railway and a greener more sustainable economy.”

Mr Inskip is chief executive of Centro, the integrated transport authority for the West Midlands.

He is also chairman of UK Tram, the forum representing Britain’s tram industry.

Work has begun on a national tram-train pilot scheme between Sheffield and Rotherham which is due to begin operating in 2015.

Mr Inskip said it was essential that transport authorities developed similar projects elsewhere around the country.

“In the Centro region alone we have three possible applications – Wednesbury- Stourbridge, Walsall-Wolverhampton and Walsall-Wednesbury,” he said.

“By starting work now in other parts of the country the successful outcomes of the national trial can be immediately captured without prolonged interruptions for lengthy project development stages.”

Bridge delivery by RRV

0

Bridge replacements have been featured in THE RAIL ENGINEER on a number of occasions. Usually these reports cover the most interesting examples of this work, as many are simply routine. New bridge arrives by road – old bridge is lifted out – new bridge is lifted in – old bridge is taken away. It’s been done in under eight hours, although a lot of preparation work goes on in advance.

However, what happens when the new bridge can’t be lifted in from the road, as there is no road access?

Dunblane difficulty

That is just what happened recently at Dunblane in central Scotland. As part of the preparatory works for EGIP, the Edinburgh-Glasgow Improvement Programme, the Bridgend footbridge near Caledonian Place was found to be foul of the proposed electrification.

Built in the nineteenth century, it was not practical to raise the existing bridge due to its dilapidated condition, nor was it possible to lower the track. The best solution was deemed to be its complete replacement. To this end, BAM Nuttall Ltd was appointed as principal contractor and work started on 2 April.

Day shift working accounted for most of the preliminary work. Over the weekend of 28/29 April, the concrete supports for the bridge were prepared by sawing and other techniques, ready for the actual bridge replacement the following weekend.

However, the complication was that there was no easy access which could be used to bring in the new bridge, and there was nowhere to site a road crane to do the lifting. It would all have to be done from the railway itself.

Plans were made to bring the bridge to the nearby station yard. Specialist plant company TRAC Engineering, based near Glasgow, were contracted to move the bridge from there to the work site.

Novel proposal

After considering the problem, TRAC’s proposal in consultation with BAM Nuttall was to move the bridge using a short train – with a difference. TRAC possesses a road-rail shunter derived from a Mercedes Unimog. Ballasted up to a gross vehicle weight of 12 tonnes, this shunter can propel up to six wagons with a total gross weight of 300 tonnes.

The shunter and five flat wagons duly arrived on site in the yard at Dunblane station, ready for a 29 hour possession commencing at 22:00 on Saturday 29 April. Two cranes were needed, a road crane from Ainscough to operate at the station end of the site, and a Kirow rail crane from Volker Rail to do the lifting at the bridge end.

At the appointed time, around 6am Sunday morning, the TRAC train departed for the bridge, where the Kirow lifted the old structure, weighing approximately 25 tonnes, from its seating and deposited it carefully along the length of the five small trucks. Once strapped down, the novel train departed for the short journey to the station and the road crane removed the old bridge to the yard.

Murdo Maclean, TRAC project manager, oversaw the reloading of his train, this time with two concrete cill units each weighing nine tonnes. These would be the spacer pieces so that the replacement bridge would sit higher than the original, allowing room for the OLE underneath. The cills were delivered to the work site and lifted into place about nine hours after the old bridge had come out, once the work to prepare their seatings was complete.

The now-empty train returned to the station yard where the smart new bridge was waiting on a low loader, and this was lifted onto the five wagons ready to be carried back to its new location.

At around 8pm on Sunday evening came the most precise part of the whole operation, as the Kirow had to lift the 15-tonne bridge from the wagons, swing it through ninety degrees and lower it precisely into place on top of the new plinths. However, no snags were encountered and everything went smoothly.

After that, it was just a question of placing the old bridge onto the low loader to be taken away, removing TRAC’s small train from the railway, and packing up the road and rail cranes. Everything was successfully carried out within the 29 hours allocated to the possession, and the railway returned to operational service on time.

John Edelsten, BAM Nuttall’s project manager was happy with the service provided by TRAC, complimenting both the site organisation and the personnel involved. With more bridge work being needed on the EGIP project, it shouldn’t be long before TRAC’s little work train is out again.

Alstom-Bombardier consortium wins one billion euro Paris contract

0

The Alstom-Bombardier consortium is to supply 210 double-deck commuter train cars for the Greater Paris network in an order worth approximately one billion euros.

The new order, which will run on line A of the RER, is an option under a contract signed in April 2009 for 60 MI09 trains.

As a consortium member responsible for one third of the order, Bombardier’s share will amount to approximately 336 million euros ($417 million US).

The new cars will be delivered between 2014 and the end of 2016.

Jean Berge, president of Bombardier Transport France, said: “Congestion is a challenge for all major cities around the world, including Paris.

“We are pleased to offer sustainable transport solutions for the future such as the MI09 trains, which we have developed together with Alstom and the RATP.

“The 200 Bombardier employees who are working on the project are highly motivated to deliver high quality rail cars on time.”

Two thirds of the project is financed by the Régie Autonome des Transports Parisiens (RATP) with the remaining funding provided by the Ile-de-France Transport Authority (STIF).

Bombardier will design and fully assemble the cars at its manufacturing site in Crespin.

Bombardier’s site in northern France employs about 2,000 people, including 500 engineers and technicians.

The consortium has designed the trains based on its MI2N trains, which it delivered for the same line between 1990 and 2000. The inauguration of the first MI09 trains on the line took place in December 2011.

The new MI09 trainsets are equipped with a more efficient traction system to reduce energy consumption and generate less brake dust because of an increased use of electric braking.

Suck it and see

0

To be called ‘the world’s most powerful vacuum excavator’ is a big claim, but that is exactly what the new RailVac RA7 is. Built and designed by the Swedish companies Railcare AB and the DISAB Group, the RA7 really does do what these companies say it will, and they have seen it in action for many years on Sweden’s railways.

That said, when can vacuum excavation be used and how does it work? For those familiar with track maintenance and renewal work, it’s easier to start by describing what the RailVac RA7 does not do. Vacuum excavation means there is:

– no need to cut rails or remove sleepers – perhaps keyhole surgery could describe the way vacuum excavation works, because the RA7 excavates between the sleepers to the required depth and width;
– no need to waste time disconnecting switches, tie-rods or crossing components;
– no risk of impacting on any highly valuable infrastructure such as existing pipework, drainage, cabling and electrics, any damage to which only exacerbates the time and cost issues involved.

Damage prevention

In seven years of using the RailVac, the Swedish company that operates it, Railcare AB, has never once had a possession over-run or even broken a cable. Any rail engineer will realise how that can benefit normal railway operations by the lack of disturbance to schedules. So how does vacuum excavation compare with traditional techniques?

Digging by hand, or excavating with mechanical tools, cannot avoid having an impact on track and the trackbed, so a CAT scan is often used in conjunction with these traditional techniques, adding to the time and cost required. By comparison, the impact made by vacuum excavation means is much less so CAT scans aren’t needed. Furthermore, with vacuum excavation, no track has to be taken up – and that’s largely why there are no over-runs with the RailVac.

Possession time is the common factor in any rail maintenance or renewal project, and the RailVac maximises valuable track possession time. With the RailVac wagon in place, excavation can start immediately. Shutdown is just as fast, so all the time is focused on repair and maintenance. Once the RailVac has done its job, and the repair is completed, new ballasting is done immediately while the RailVac takes away all the old ballast it has vacuumed for disposal.

Undercutting is another form of traditional excavation technique. However, while faster than doing things manually, it takes far longer than vacuum excavation and doesn’t cope with compacted material like clay.

Anything goes

On the other hand, the massive suction power of the RailVac will handle any material, as seven years of successful operation has proven. Basically, anything that fits up the RailVac’s hose – goes. The RailVac’s 225mms diameter flexible suction hose has a metallic end pipe which is manoeuvred by a hydraulically-operated excavator arm. Just one operator controls this (think of a PlayStation console!) while standing close enough to see what’s going on at the sharp end.

Typical repairs that demonstrate the benefits of using a RailVac are:
switch and crossing units, which normally need the track to be cut back, taken out and lifted, while 300-400mm of ballast is removed and a new unit is installed and ballasted. Typically, this requires 16 hours and a 12-man gang, with a 24 hour possession and all the subsequent impact and disturbance to normal running schedules. The RailVac doesn’t need to work this way; 300-400mm of spent ballast can be removed with everything else in place and a C, D or E crossing fitted over four 3-4 hour shifts of track possession time during the week, so there is no disruption to normal schedules nor any need to disturb weekend running either.

Other typical repair examples include plain line re-ballasting, drainage installations, level crossing refurbishments, and under track crossing (UTXs). A RailVac can vacuum excavate a double track UTX in 20-30 minutes, up to 1.5 metres below the sleepers and with no disturbance to the sleepers or normal operational schedules.

The number of operatives required on site also underlines the RailVac’s advantages over traditional techniques. A typical track repair usually needs upwards of a dozen men. The RailVac needs fewer – just a controller, two other RailVac operatives and a small gang for jacking and packing. Using a RailVac can be safer for as well.

On a recent trial at Beeston in Nottinghamshire, a Gv crossover was replaced with the RailVac excavating 300mms below the track. The operation took 8 hours in total – just two four hour possessions for each unit, with no interruption to normal daily operational schedules.

UK specific

The RA7 RailVac unit is Railcare AB’s first bespoke air/vacuum excavator, or to give its full name, a Ballast Vacuum Extraction System (BVES), for the UK market. Designed and built in partnership with the most powerful vacuum equipment available from the DISAB Group of Sweden, it conforms with W6A loading gauge standards. In wagon mode the RA7 can be dead hauled in train formation, and when in a track possession situation and working in the self-propelled mode, it is classed as on track machine (OTM).

The RA7’s suction power comes from two Caterpillar C9 diesel engines, two vacuum pumps and two air compressors, creating an impressive 19,000 cubic metres of air flow per hour at around 95% vacuum efficiency. The machine’s flexibility comes from a manipulator arm for excavation and a unique hydrostatic transmission system that is powerful, reliable and precise in its operation. There are about 40 identified RailVac applications suitable for the UK, some of which are already creating benefits for Network Rail.

The braking system on the RA7 is controlled from all driving/operating positions. To reduce the risks of injury to personnel and damage to the infrastructure, a number of emergency safety systems have also been built into the machine.

A Network Rail Engineering Acceptance Certificate (EAC) was issued early in 2012 and the unit can now provide ballast excavation services for infrastructure owners and maintainers all over the UK. Network Rail has already granted Railcare AB a certificate of Full Product Acceptance for the RailVac method of work.

RailVac excavation services in the UK are supplied by Bridgeway Railcare LLP, a collaboration between Bridgeway Consulting Ltd in the UK and Railcare AB of Sweden. As a specialised contractor, Railcare AB is now investing heavily in the UK railway market. Coming from Sweden, where the 7 day railway philosophy is already a reality, Railcare AB’s methods are not only innovative but very well placed to help the UK’s railway operators and owners make a dramatic difference to the traditional techniques, time and costs of track maintenance and renewals.

Indian Railways launch train tracking text service

1

Indian rail passengers are now able to track their train in real time with a new SMS service.

Indian Railways and the Indian Institute of Technology (IIT) Kanpur have launched the new service, which allows customers to find out where their train is simply by sending a text message.

The service is currently available for 36 premier trains including Mumbai Rajdhani, Howrah Rajdhani, Dibrugarh Rajdhani, Sealdah Duronto and Shatabdi trains for Bhopal, Kanpur and Amritsar.

Indian Railways’ technology arm, Centre for Railway Information Systems (CRIS), will soon sign a Memorandum of Understanding (MoU) with IIT-Kanpur for executing the project.

Indian Railways expects to extend this facility to all major trains in the next 18 months.

For this service, Indian Space Research Organisation’s (ISRO) S-Band mobile satellite service (MSS) on INSAT-3C and GPRS will be used.

Apart from launching the train tracking system through Trainenquiry.com in partnership with RailYatri.in, Railways is also working on a system that will track trains via GPS known as Satellite Imaging for Rail Navigation (SIMRAN).

The project has been in operation since October 2011 on selected trains. Users were able to track train locations either via simran.in or SMS.

The SIMRAN project is being built in collaboration by Research Design and Standards Organisation (RDSO), Lucknow and IIT Kanpur.

Simple safety

0

Safety fencing. It’s something that’s always around, yet no-one sees. It needs to be put up at the start of almost every lineside job, and taken down afterwards, but other than that it’s just there – like sleepers and ballast.

However, it needs to be put up quickly, as everyone else is waiting to get on with the job, and taken down even more quickly if the work is running a little late and the hand-back time is approaching.

So what is needed is a simple, even foolproof system. It also has to be light, easily transportable, and to do the job of separating people from trains.

Lightweight safety fencing, which fastens to a track while protecting people working in the cess or on an adjacent track, is not new. There are several systems on the market which clip to the rail in one way or another, but now there is one which is even simpler, and doesn’t use clips at all. Instead, it capitalises on two of the great facts of life. Rails are made out of steel, and steel is magnetic.

The new Magnetic Safety Barrier from Rail Safety Systems (RSS) has been brought to the UK by Innovative Railway Safety. Based in Swansea, they are specialists in such equipment and know a good safety system when they see one.

What is it?

A square-section steel tube, zinc-plated to protect it from the elements, is fitted with a broad black plastic head containing two powerful magnetic strips. When this head is attached to the web of the rail, the tube extends horizontally out from the side of the track. As the head is hinged, some vertical movement of the tube is possible and the tube itself is shaped with a double kink which rests on the top of a sleeper and keeps the tube approximately horizontal.

At the other end, a sleeve fits over the tube. This then curves upwards to form a vertical stanchion, again in lightweight square-section steel tube. The actual position of the stanchion is adjustable – the sleeve can slide along the horizontal tube and is bolted in place using a series of pre-drilled holes. As standard, there is a total of 600mm of possible adjustment, allowing the fence to be positioned the correct distance from the running track.

On the outer face of the vertical stanchion are two, pre-positioned plastic clips. Once a row of stanchions is in place, horizontal poles can be clipped into these, forming the fence itself. Both fibreglass and aluminium poles can be used – if aluminium then there are plastic isolators along its length to prevent any problems with the metal poles bridging signalling circuits.

Installation

Poles and stanchions are transported to site in specially designed bins. Normally, the horizontal tubes and vertical stanchions are already bolted together with the correct clearance. These are then simply clamped, about three metres apart, to the side of the rail web over a sleeper on which the kink in the horizontal tube rests. The installer never has to go close to the running rail, but can stand in a position of safety holding the vertical stanchion while attaching the magnets to the rail.

Once a run of stanchions is in place, the first fence poles are clipped in place. Subsequent poles are attached using a patented bayonet connection and clipped up. A team of people, working together, can install a run of fencing remarkably quickly. Once they get into the swing of things, and assuming the stock of components is close by, several hundred metres can be erected in just a few minutes. No ballast needs to be disturbed – provided that the rail web is accessible, the fence can go up.

In operation, the strong magnetic clamps hold the fence securely in place. It is practically impossible to just pull the magnet off the rail, so work can take place behind the fence in complete safety.

Removal

Taking the fence down is almost a reversal of putting it up. The poles are removed first, the bayonet couplings making splitting it into short lengths easy.

Despite the magnetic clamps being almost impossible to pull off in service, removal is actually quite easy. The stanchion, and it’s attached horizontal pole, is just pivoted up vertically. This assembly hinges on the magnetic head until that hinge hits a stop. Continued upward movement rolls the magnet off the rail – the head has a radiused upper edge to allow this. So the whole bracket comes free without undue effort.

Then it is only a case of putting everything away and removing it from site. As no ballast was disturbed in erecting the fence, there is nothing to be replaced.

Critical acclaim

The Magnetic Safety Barrier was first introduced onto the Dutch railway system in 2010. In March 2011, it won the Europe Innovation Award at the Rail-Tech Europe trade fair in Amersfoort. “All together, the crucial significance of safety for employees performing maintenance work on the track was reason enough for the jury to send Rail Safety Systems home with the 2011 European Innovation Award”, said jury chairman Professor Riessberger.

The new fencing has been tested by TÜV and is approved for use in Germany and is now also approved by Network Rail for use in the UK. Initial use has found that is can be up to twenty times quicker to erect and dismantle than conventional barriers, reduces the physical effort of the operatives and the ballast is not disturbed. Installed correctly, it does not affect axle counters or DC track circuit signals.

Innovative Railway Safety arranged the first major use of the new fencing in the UK last month and, with the advantages that Magnetic Safety Fencing offers, no doubt it will shortly be appearing on a work site near you. Once erected, it still won’t be noticed, but it will certainly appear and disappear a lot quicker!

Green light for York Ops Centre

0

City authorities in York have agreed Network Rail’s plan to build a new rail operating centre and workforce development school close to York station.

Says Phil Verster, Route Managing Director, ‘This decision is great news for York and the railway. These operating and training facilities will allow us to deliver a modern, efficient railway while at the same time maintaining York’s position as a proud rail city.

‘The centres will retain jobs in the city and, over time, see all of our rail operations for the LNE route consolidated on this site.

The operating centre is the largest of just 14 proposed centres across Britain and will bring the expertise and technology we need to operate the route into a single location.

Meanwhile the investment in modern training facilities will make sure our rail employees remain among the best in the world.’

The land identified for development is known as the engineer’s triangle and lies between York station and Holgate bridge.