Mid Hants Link rail trial halted due to ‘catastrophic electrical failure’

Listen to this article

GO! Co-operative Limited has announced plans to reschedule its postponed ‘low carbon’ local rail service in Hampshire.

GOCO is in on going negotiations with partners including Hampshire County Council and Mid Hants Railway, and with their continued support, plans to reschedule the resumption of the trial later in 2011.

The Mid Hants Link trial was originally scheduled to proceed in January 2011 but was delayed due to technical issues affecting the lightweight railcar.

The railcar suffered damage to its electrical system in transit and as testing began, a hydrostatic pump suffered a catastrophic failure which could not be repaired within an acceptable timeframe.

Chris Phillimore of GOCO said:

“Reluctantly and understandably, GOCO and our partners took the decision to suspend the trial until the technical issues with the railcar could be fully resolved and we could offer a reliable service.

“We remain even more determined to develop Ultra Light Rail projects in the United Kingdom. The knowledge and expertise we have gained in developing and promoting the Mid Hants Link has made us even more convinced of the business case for Ultra Light Rail, based on co-operative principles.”

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Latest Rail News

New trains named after Wrexham Football Hollywood stars

Transport for Wales has named two new trains after the home cities of Wrexham Football Club owners Ryan Reynolds...

More like this...