RAIB: Carmont derailment due to faulty drainage work

Listen to this article

The Rail Accident Investigation Branch (RAIB) has released its report into the fatal derailment of a passenger train at Carmont, Aberdeenshire, 12th August 2020.

At around 09:37 hrs on Wednesday 12 August 2020, the 06:38 hrs service from Aberdeen to Glasgow derailed near Carmont, Aberdeenshire. It was travelling at 73 mph, just under the normal speed for the line concerned.

After derailing, the train deviated to the left, before striking a bridge parapet which caused the vehicles to scatter. Tragically, three people died as a result of the accident: the conductor, Donald Dinnie; the train driver, Brett McCullough; a passenger, Christopher Stuchbury. The remaining six people on the train were injured.

On the morning of the accident there was near-continuous heavy rain at the site of the accident between about 06:00 hrs and 09:00 hrs. The 51.5 mm of rain which fell in this period at the accident site was close to the average rainfall for the month of August in this part of Scotland.

Train 1T08 derailed because it struck debris that had been washed out of a drainage trench.

The trench, which had been constructed between 2011 and 2012, contained a perforated pipe that had been installed as part of a project to address a known problem with drainage and the stability of a cutting in that area. However, the drainage system and associated earthworks had not been constructed in accordance with the original design and so were not able to safely accommodate the water flows that morning.

RAIB’s investigators found that a low earth bank (bund) had been constructed that ran across a slope leading towards the track. The presence of this bund significantly altered the flow of water such that extreme rainfall would cause a concentrated flow into the steeply sloping section of trench. The evidence indicates that the intensity and duration of this rainfall would have generated water flows into the trench that were sufficient to wash away the gravel fill and the ground immediately surrounding the trench.

No instruction was given by route control or the signaller that train 1T08 should be run at a lower speed on its journey between Carmont and Stonehaven. At that time there was no written process that required any such precaution in these circumstances. Consequently, normal railway rules were applied to the train movement. The RAIB’s investigation found that the ‘route controllers’ (who were responsible for the operational management of Scotland’s railway network) had not been given the information, procedures or training that they needed to effectively manage complex situations of the type encountered on the morning of 12 August 2020.

The RAIB’s investigation also identified that Network Rail’s management processes had not identified or addressed weaknesses in the way it mitigated the consequences of extreme rainfall events. Furthermore, despite an awareness of the risk, Network Rail had not completed the implementation of additional control measures following previous events involving extreme weather and the management of operating incidents.

A train built to modern standards would have had a number of design features that are intended to minimise the damage to the train in case of collision or derailment. However, the refurbished HST that derailed at Carmont was designed and constructed before some of these standards came into force. While it is not possible to be certain about what would have happened in the hypothetical situation with different rolling stock in the same accident, RAIB considers it more likely than not that the outcome would have been better if the train had been compliant with modern ‘crashworthiness’ standards.

Recommendations

As a consequence of this accident, RAIB has made 20 recommendations for the improvement of railway safety. The areas covered include:

  • Better management of civil engineering construction activities by Network Rail and its contractors
  • Additional standards and guidance on the safe design of drainage systems
  • Improved operational response to extreme rainfall events, exploiting the full capability of modern technology, and based on a detailed understanding of the risk associated with extreme rainfall
  • Enhancing the capability of route control offices to effectively manage complex events
  • Extending Network Rail’s assurance regime to encompass route control offices
  • Addressing the obstacles to effective implementation of lessons learnt from the investigation of accidents and incidents
  • Measures to prevent derailed trains from deviating too far from the track (equipment fitted to track and/or trains)
  • Addressing train design issues identified by the investigation and better understanding the additional risk associated with the operation of older trains.


Simon French, the Chief Inspector of Rail Accidents, said: “This was a tragedy that devastated the lives of the three families who lost their loved ones and brought terror and injury to six other people on the morning of 12 August 2020. Our thoughts are with them all. Nothing can undo this event, but we owe it to everybody who was affected by it to strive to learn safety lessons for the future.

“Although railway safety in the UK has been steadily improving over recent decades, the tragedy at Carmont is a reminder of just how disruptive and potentially dangerous Britain’s volatile weather can be. The railway industry needs to get even smarter about the way it counters this threat, and to better exploit remarkable modern technology that enables the prediction and tracking of extreme weather events such as summer convective storms. There’s also an urgent need for the railway to provide real-time decision-makers with the information, procedures and training they need to manage complex and widespread weather-related events across the rail network.

“No one wants to shut down the railway every time it rains. Railways need to operate safely and reliably in most weather conditions. If they’re not able to achieve this, potential passengers will be forced onto the roads, which are undoubtedly much more dangerous in bad weather conditions. So, there’s a balance to be struck and technology can help to get this balance right. Modern weather forecasting and monitoring systems can spot the truly exceptional events before they occur and as they happen, so allowing railway operators to implement precautionary measures when it’s prudent to do so. This would benefit the safety of the line (by restricting train speeds, or suspending operations, when necessary) while reducing the need for imposing blanket speed restrictions over areas that are not at significant risk.

“This investigation highlights the risk of uncontrolled changes to railway infrastructure during construction. It is so sad that a project that was designed for the protection of the travelling public became unsuitable for its intended use and posed a hazard to trains because of such uncontrolled changes to the design. When anything is built in difficult conditions, such as on the side of a steeply sloped cutting, changes will often be needed for practical reasons. Although such changes are normal and can be highly beneficial in terms of saved time and cost, they need to be made with care. In each case, the original designer needs to understand the change that’s proposed and review the implications of a change that may appear inconsequential to the team on site. I hope this example will resonate throughout the UK’s construction industry.

“It’s important for all of us in the rail industry not to dismiss this truly harrowing accident as a one-off event. The railway industry needs to think through the implications of severe weather on its infrastructure, whilst also looking to the behaviour of trains should they derail after striking obstructions such as washouts and landslips. Is there more that could be done to keep trains in line and closer to the track, to minimise the risk of jack-knifing and to keep bogies attached to rail vehicles? RAIB doesn’t have all of the answers but is urging the railway industry to think about ways of guiding derailed trains, and to think about the longer-term implications of continuing to operate rolling stock that pre-dates modern standards.”

Image credits: RAIB

Latest Rail News

ORR review leads to 50% reduction in maximum fees for ticket refunds

New rules will mean that from 2 April the maximum fee that train operators and ticket retailers can charge...

More like this...